Time Line

August 31 - Signed Contract

September 7 - Met with Loan officer (NVR)

September 14 - Met with Guardian

September 16 - Met with Rite Rug

September 25 - Loan Submitted to Underwritting

September 28- Received Loan Approval!!!

October 22: scheduled preconstruction meeting

October 26: Preconstruction Meeting

November 7: Broke ground!

November 8: Footers pored

November 9: Footer forms removed, Sump pump/plumbing installed

November 15: forms for basement walls installed and concrete poored. Gravel filled in the basement

November 16: Forms removed!

November 19-20: Plumbing in basement installed, driveway and garage filled in with gravel (!), waterproofing completed around the house, right side of house back filled. 

November 21: Left side of house backfilled. plastic installed over gravel.

November 28: bathtubs and steal beams dielivered.

November 29: Wood delivered. Basement and garage floors poored.

November 30: Framing begain! First floor was completed  :)

December 1st: 2nd floor framing completed- Just waiting for the roof!

December 3rd: We have a roof!!

December 5th: Happy Birthday to Me! Garage Door installed and Front porch/stoop pored.

December 8th: walk through with guardian to mark out places for upgraded electrical.

December 9th: Shingles Installed

December 10th -13th: Ellectrical and plumbing installed through out the house. 

December 17th: Predrywall meeting & locked in mortgage rate

December 19th: Scheduled final walthough and closing day & time =]

December 20th: Bad weather (BOOO)...pending visit to find out what is done on the house

December 20th - January 1st: drywall/taping mudding completed. Cabinets and railings delivered. Interior doors delivered. Exterior siding started.

December 29th: Ordered our refrigerator and purchased new cook ware! Also ordered the Cat Genie (Cat toilet). 

January 2nd: Wood floors installed in kitchen and foyer, vinyl flooring installed in all four bathrooms, Entire house painted (beautiful grey color we picked out), Siding completed, shutters installed on two windows, and they started prepping to lay the stone :) 

January 29th 9am: Final Walkthrough

February 1st 10AM: We get our keys!!!!!!!!!! 